[ARCHIVED] South Lake Tahoe Roadway Construction Update for July 21-27, 2013

U.S. Highway 50 (El Dorado County) in South Lake Tahoe: Work continues on completing a $43 million water-quality and roadway improvement project from the Trout Creek Bridge to Ski Run Boulevard. Landscaping, striping and electrical work is scheduled for summer 2013. Completion is expected in early fall.

U.S. Highway 50 (El Dorado County) in South Lake Tahoe: Work continues on a $7.3 project from just west of Ski Run Boulevard to Wildwood Avenue adding curbs, gutters and new drainage systems and repaving the highway. Completion is expected by 2014.

U.S. Highway 50 (El Dorado County) from Fairway Avenue to Wildwood Avenue: Eastbound and westbound motorists can expect alternating lane and shoulder closures from 11:30 p.m. Sunday to 10 a.m. Monday, 10 p.m. to 10 a.m. Monday through Thursday and 10 p.m. Thursday to 9 a.m. Friday. A contractor is scheduled to do drainage work.

U.S. Highway 50 (El Dorado County) in South Lake Tahoe: Work continues on a $12.1 million project from the "Y" intersection of Highways 50 and 89 to the South Lake Tahoe Airport adding curbs, gutters and new drainage systems and repaving the highway. Completion is expected by 2014.

U.S. Highway 50 (El Dorado County) from F Street to the "Y": Eastbound and westbound motorists can expect alternating lane and shoulder closures from 8 p.m. to 11 a.m. Monday through Thursday and 8 p.m. Thursday to 10 a.m. Friday. A contractor is scheduled to do drainage work.